NEWS, January 2024 Unique living experience by the lake

Our construction project at Albertusse continues to grow - even over the winter months. The interior plaster has already been applied in the first residential building (House 3A) and the drywall work has been successfully completed. We are currently laying the underfloor heating there so that the screed work can begin next. In the coming months, the floor coverings and fine installations will then complete the interior work. We are also working at full speed in house 3B: the focus here is currently on the interior plastering and drywall work.

In addition, the final ceilings will be concreted in houses 7 and 8 at the beginning of February. After the initial sealing work on the roofs, we will install the windows and patio doors in mid-February. The interior work will then begin with the first interior plastering.

The shells of houses 1, 2, 5 and 6 are also taking shape. 

In addition to the current construction progress, you will also find a selection of pictures in our gallery that our project team took at the beginning of January when it was snowing in Düsseldorf. One thing is clear - living at Albertussee has year-round charm:

Contact